2013 Perimeter Fence Replacement

Phase 7 of the perimeter fence project started January 7th and replaces approximately 4,795 feet of fence along Crestline Avenue. The construction phase will take about 12 weeks depending on weather. When phase 7 is complete about 33,800 feet of original perimeter fence will have been replaced. The remaining 8,800 feet is planned for replacement in 2014 and 2015.